Boarding is the point of no return. What makes it expensive is whatever was not finished before it.

A bathroom stripped to studs and subfloor with new framing and blocking in place

What this involves

Drywall

Boarding is the point after which everything behind the wall is expensive to reach again. Once drywall is up and taped, accessing the cavity means opening it. Opening it means reopening the work, refinishing, and living with disruption.

What has to be genuinely complete before the walls close is every service, every rough-in, every blocking decision. Plumbing has to be rough-in complete. Electrical has to be in place. HVAC has to be ducted. Insulation and vapour barriers have to be installed. Every one of these is expensive to add after drywall closes them in.

Protecting new board from the wet trades that follow is a practical detail. Waterproofing, tiling, all the processes that bring water into the bathroom happen after boarding. New board has to be protected from this water during construction. Sealing it or putting up protection prevents damage while the finishes are being installed.

Reopening a closed wall is the failure this stage exists to avoid. The cost in time and disruption is enormous. A missed service, a forgotten blocking detail, a miscommunication — all of these become reopening projects if discovered after boarding. The stage is designed to catch these before boarding closes them in. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This ensures quality outcomes. This e

  • Licensed & insured
  • WorkSafeBC coverage
  • Written quotes & contracts
  • Built to BC Building Code

Why it matters

What you get

Boarding closes everything behind the wall — this is the finality point

Once drywall is up, the cavity is closed. Accessing it means opening the wall. Opening it is expensive and disruptive. This stage is the point of no return. Everything behind the wall has to be complete before boarding starts.

What is complete before boarding is: all rough-ins, all blocking, all services

Plumbing rough-in complete. Electrical complete. HVAC ducted. Insulation installed. Vapour barrier installed. Blocking installed. All of this is done before drywall goes up. Nothing is deferred or assumed to be done later.

New board has to be protected from water and construction activity during finishing

Waterproofing, tiling, and finishes all involve water. New board has to be sealed or protected during this work so it does not absorb water and fail. Protection during construction prevents damage.

Reopening a wall is the outcome boarding is meant to prevent

A missed service, a forgotten blocking detail, a miscommunication — if any of these is discovered after boarding, the wall has to be opened. This is expensive in time, money, and disruption. Completeness before boarding prevents it.

How it runs

The process

  1. 01

    Verify that all rough-ins and services are complete before boarding starts

    Plumbing has to be done. Electrical has to be done. HVAC has to be done. Insulation and vapour barrier have to be installed. Blocking has to be complete. Walk the space and confirm everything is done.

  2. 02

    Close the cavity with the understanding that this is the point of no return

    Board is hung. The understanding is clear: nothing behind the wall can be changed now without opening it. Everything had to be right before this stage.

  3. 03

    Protect new board from the wet trades that follow

    Board can absorb water during waterproofing and tiling. Protect it with plastic, sealing, or other methods so it stays dry during construction.

  4. 04

    If something is discovered after boarding that should have been done before, the wall opens

    This is the last-resort outcome. The wall is opened, the issue is fixed, and everything is refinished. This is expensive and is the reason completeness before boarding is critical.

Questions

Frequently asked

All rough-ins: plumbing, electrical, HVAC. All blocking from the framing list. All insulation and vapour barrier installation. Every service and every structural detail. If it should be behind the wall, it has to be done and verified before boarding.

Reopening means cutting drywall, accessing the cavity, fixing the issue, and refinishing. It disrupts the schedule, adds cost, and creates quality issues. This is the outcome boarding is meant to prevent.

Covering with plastic sheeting, sealing with primer or protective coatings, or other methods. Waterproofing, tiling, and finishing all involve water. Board has to stay dry during construction.