An enclosure is an assembly of glass, blocking and seals, and the part that eventually fails is almost never the glass.

A tiled walk-in shower with a frameless glass panel, linear drain and a recessed niche

What this involves

Shower Enclosures

Glass arrives as a rectangle. Walls in a house that has settled for fifty years are not rectangles, and the gap between those two facts is where most enclosure trouble begins. The choice between frameless, semi-frameless and framed follows from two questions: how much of that discrepancy each system can absorb, and what is going to hold the glass up.

Frameless glass transfers its whole load into the wall, so the wall has to have been built for it. A 10 or 12mm panel is heavy, and it hangs off two or three clamps or sits in a channel fixed through tile into whatever is behind. Fixings that rely on tile and drywall will move, and once a clamp shifts the panel is out of alignment and stops meeting its seal. The answer is solid blocking let into the studs at the clamp and hinge heights, which has to go in while the walls are open, months before anyone measures glass.

Plumb tolerance decides the system as much as budget does. A framed enclosure carries an aluminium jamb up each wall that can be packed and adjusted, so it will close out a wall several millimetres out of true. A semi-frameless unit uses a header across the top to support thinner glass and keeps some jamb adjustment. Frameless has almost none: a panel set against a wall 10mm out over two metres leaves a wedge-shaped gap no seal will bridge. Either the wall is made plumb before tiling, or a channel is used to conceal the discrepancy, or the frameless look is not available in that room.

Seals are directional, which is where enclosures are most often got wrong. Sealant at the foot of a panel belongs on the outside face only, so anything that tracks behind the glass drains back into the shower instead of sitting against the tile edge. A drip rail under a swinging panel is angled inward for the same reason. And templating happens after tiling, against the surfaces the glass actually has to meet.

  • Licensed & insured
  • WorkSafeBC coverage
  • Written quotes & contracts
  • Built to BC Building Code

Why it matters

What you get

Blocking fixed while the walls are open

Clamp, channel and hinge heights are worked out during framing so every fixing lands in solid timber instead of in tile and a plastic anchor.

The system matched to the walls

How far out of plumb the walls actually run is measured before a system is chosen, because that single number decides whether frameless is available at all.

Water sent back into the shower

Sealant runs on the outside face and drip rails angle inward, so anything getting behind the glass drains in rather than pooling against the tile edge.

How it runs

The process

  1. 01

    Check plumb and set blocking

    Every wall the glass will meet is checked top to bottom, and timber is fixed between the studs at the heights the intended hardware needs before anything closes.

  2. 02

    Choose the system to suit

    Frameless, semi-frameless or framed is settled against the measured walls, the panel spans involved and how the opening actually has to be closed off.

  3. 03

    Template and install to finished walls

    Panels are measured against tiled surfaces, fabricated to those figures, then hung on hardware bolted into the blocking and sealed on the outside face.

Questions

Frequently asked

Because it has to fit the finished surfaces, not the drawn ones. Tile thickness, the adhesive bed, a wall packed straight and a curb that ended up wider all change the dimension a panel needs, and tempered glass cannot be trimmed once it exists. Measuring off a plan produces panels a few millimetres out, which is precisely the amount that will not seal.

The clamps pass through tile, but they cannot rely on it. Tile and drywall have very little holding power against the leverage of a heavy panel leaned on every day, and a fixing that seems fine for a year works loose in three. Continuous timber behind the tile, set at the clamp and hinge heights during framing, carries the panel. Adding it later means removing tile, which is why the hardware layout is decided long before the glass is.

Usually because the panel was sealed on both faces. A bead inside and out makes a closed cavity underneath, and the water that inevitably tracks in has nowhere to leave, so it sits there and grows something. Sealing only the outside face leaves the inside open, and whatever gets under the panel runs back into the shower and down the drain. Raking out the inner bead is the repair, and it is a small detail that decides whether the joint stays clean.

Working out how the glass gets held up?

Wall plumb and blocking positions get checked first, because between them they decide which enclosure systems are genuinely available.